Warro-5 flows Gas Testing to Start

January 11, 2016

 

Transerv Energy informed that fracture stimulation work has been successfully concluded at the Warro-5 well in WA’s Mid-West. The Warro-5 and Warro-6 wells are now being completed in preparation for long term gas testing.

Warro-5 stimulation operations were completed on 7th January and all the equipment is now being demobilized from site. The final, second stage at Warro-5 resulted in the 305,000 pounds (138,400kg) of proppant being placed in the gas reservoir. Combined with the deeper Stage 1, Warro-5 has injected 385,000 pounds (175,000kg) of proppant over an interval 4330 – 4410mRT.

Clean-up flows at Warro-5, conducted over the weekend yielded a sustained gas flow with a continuous flare. Like Warro-6, the gas rate could not be measured. This will be done once metering equipment, required for the extended testing programme, is installed.

At Warro-6, the Enerdrill workover Rig 1 is now preparing to run 2 3/8” production tubing a>er which a jet pump will be placed in the well to assist with the recovery of any liquids. An identical completion will be installed immediately afterwards at Warro-5. Gas flow testing is expected to commence at both Warro-5 and 6 wells during the second half of January 2016 and is planned to continue through Q1 and Q2 2016.
 

Related News

Marine Technology ENews subscription

World Energy News is the global authority on the international energy industry, delivered to your Email two times per week.

Subscribe to World Energy News Alerts.